# | Date | Sections | Topic | Due | Lab |
1 | Wed Jan 18 | -- | Uncertainty calculations | -- | |
2 | Mon Jan 30 | 3.1-3.5 | Electronic noise | -- | |
3 | Wed Feb 1 | -- | Discussion of projects Uncertainty - student presentations | Assignment 1 | |
4 | Mon Feb 6 | -- | Project descriptions | -- | |
5 | Wed Feb 8 | -- | Electronic noise - student presentations | Assignment 2 | |
6 | Mon Feb 13 | -- | Project discussions | -- | |
7 | Wed Feb 15 | -- | Projects presentations 1 | Assignment 3 Presentation slides Honeywell HMC 2003 Radiation dosimeters RADFET datasheet Chad Lindstrom dosimeter paper MSP430 datasheet Proposed satellite power supply Proposed satellite CPU board | |
8 | Mon Feb 20 | 3.10 | Interference and its minimization | -- | |
9 | Wed Feb 22 | -- | Project Presentations 2 | Assignment 4 | |
10 | Mon Feb 27 | 3.10 | Interference and its minimization | -- | |
11 | Wed Feb 29 | -- | Project Presentations 3 | -- | |
12 | Mon Mar 5 | 6.9 and handout | Radiation sensors | -- | |
13 | Wed Mar 7 | 6.9 and handout | Radiation Sensors and Space Particle Instrumentation Project Presentations 4 | -- | |
14 | Mon Mar 19 | -- | Project discussion | -- | |
15 | Wed Mar 21 | -- | Project presentations 5 | -- | |
16 | Mon Mar 26 | 6.3 | Resistive temperature sensors | -- | |
17 | Wed Mar 28 | 6.4 | Voltage-generating sensors Project discussion | -- | |
18 | Mon Apr 2 | 6.6, 8.10.2 | Capacitive sensors and capacitance measurement | -- | |
19 | Wed Apr 4 | 6.7 | Fiber optic sensors Project discussion | -- | |
20 | Mon Apr 9 | -- | |||
21 | Wed Apr 11 | Project details | Sections 1, 2, and a draft of sections 3 and 4 | ||
22 | Mon Apr 16 | Sections 3 and 4 complete, draft of section 5, revisions | |||
23 | Wed Apr 18 | -- | |||
24 | Mon Apr 23 | Section 5 complete, draft of section 6 and 7, revisions | |||
25 | Wed Apr 25 | -- | |||
26 | Mon Apr 30 | -- | Final presentation | Initial version of final report | |
27 | Wed May 2 | -- | Final presentations | -- | |
-- | Fri May 4 | Second version of final report, if needed | |||
-- | Mon May 7 | Final report |